January 10th, 2025 progress Maintenance Mezzanine Meeting room from front of building Bathroom Kitchen from meeting room Maintenance building and drive through Front of building
Latest progress on the Maine Trail Center as of 10/20/2024 - Main building is basically closed in - Crew cabins are 3/4's shingled - All exterior sheathing done - Interior walls frame - Wiring rough in nearly complete - Road definition complete, only final grading and reclaim remain
Latest update on the Trail Center: - Crew cabins have electricity, and Cabin 2 cleaned, floor painted, and inventory moved from Lake George into Cabin 2 for the winter - 2 days of work to complete crew cabin shingling remain - Roof is in progress - Siding to be installed - Final grading and reclaim installed on access road